Gainesville Fire Rescue Station #9
Additional Info
Award Winner : Vesta Modular
Architectural Excellence : To accommodate the massive growth on the East Side of Gainesville, the town’s fire department needed to build a fire station in the new development area known as Butler Plaza. The building needed to meet the architectural requirements of Butler Plaza and the operational requirements of the Fire Department while being built quickly and on budget. VESTA met with the Fire Department and the Butler Plaza architectural review board to design an architecturally compliant exterior glazing and finish to blend in with the commercial development community.
Cost Energy Effectiveness : VESTA Modular, Titan and Gainesville Fire Rescue collaborated to design a cost-effective facility to meet the needs of the community, the architectural committee and the requirements of the stationed fire fighters. The effective use of offsite construction provided for site development while permitting and construction of the building took place. The time savings was approximately 10-12 months faster than conventional site build methods. This process provided for speed of design and execution as a cost-effective method for the Fire department.
With design efficiencies of the modular building process and approvals, 9 months of design and approval expectations were reduced to 30 days. Butler Plaza approvals and building department plan and site approvals were completed in what seemed to be record time.
Installer Firm Name : VESTA Modular
Occupied Date : 9/5/2017
Owner Firm Name : City of Gainesville, Florida
Production Start Date : 4/15/2017
Project Location City : Gainesville
Project Location State Name : FL
Technical Innovation : VESTA contracted with Titan Modular Systems, Inc. to design fire station #9 according to the crew requirements with bunk rooms, day room, equipment room, kitchen, and office space based on the Florida R2 code for emergency personal using standardized modular construction means and methods. The configuration allows fire fighters to move within the building without any obstructions to access the response apparatus (Fire Truck). Each space has direct hall access to the apparatus bay.
Total Square Feet : 2460