Chateau Bellevue
Additional Info
Award Winner : Corner Cast Construction Inc.
Architectural Excellence : Corner Cast was asked to provide an appealing condo sales office with minimal budget and only 2 weeks delivery time. The solution was found by re-using two former office units with an autonomous toilet system, that were able to create the look and functionality required.
To achieve the overall look and feel of the condominium development, while largely conserving the existing interior finish, accents were brought on with new trims, a separation screen, faux wood beams and matching interior doors. This, in combination with a new hardwood floor laid in a large herringbone pattern throughout both units, gave the desired modern and warm feel to the interiors.
For the exterior appearance, the original exterior was conserved. However, by re-painting the modules black and adding an 8’ x 20’ portico, the focus was brought the main entrance, providing a visually attractive frontage.
Cost Energy Effectiveness : By re-using an existing steel structure and its interiors, the client was able to have a working sales office within 3 weeks, saving the customer money & moving the project forward without delay. This process was completed without making any concessions to the look, and therefore the client was able to offer an attractive space for condo sales to their prospective clients.
Green Building Description : With the exception of the replaced floor, minimal waste was created thanks to ingenious interior re-design. With the units already been recycled containers and the interiors done with high efficiency LED lighting, zone D certified windows and energy star rated ventilation systems, maximum thermal comfort & low operational costs remained intact and make the units ready for many future usages with minimal environmental impact.
Occupied Date : 2/26/2021
Owner Firm Name : BBCF
Production Start Date : 2/10/2021
Project Location City : Quebec City
Project Location State Name : Quebec
Technical Innovation : The original modules were fabricated by recycling 2 x 40’ HC used containers. The interiors were completed with high efficiency LED lighting zone D certified windows and energy star rated ventilation systems. All these elements were preserved in order to ensure thermal comfort & low operational costs. The autonomous plumbing system makes the units extremely flexible for different usages and can be placed in any location.
The main driver for this renovation project, was the lead time. The units were redesigned and renovated within 2 weeks in the factory in Montreal and then transported to site for a total construction time of less than 3 weeks.
The installation of the complex was done on standard, recycled 2’x2’4' concrete blocks, making it very easy to re-locate. Once the construction of the condo development is complete, the units can be easily disassembled.
Due to the structural integrity of the Corten steel the shipping containers can be re-used for many years to come.
Total Square Feet : 800